Spread over two sites in Hatfield, the University of Hertfordshire is home to more than 24,500 students, including 3,400 who live on campus in the halls of residence.


The University takes its environmental responsibilities seriously and is ranked 15th in the 2009 People and Green Planet universities league table.


It already has a Carbon Management Plan in place with plans to help meet the targets set out by the Higher Education Funding Council for England (HEFCE), which require the sector to reduce Scope 1 and Scope 2 emissions by 43% by 2020.


For the University this equates to saving approximately 20,000 tonnes of carbon per annum by 2020, based on 2009 emission data.


The University’s Carbon Management Plan includes the introduction of a CHP system to the central district heating system on the main campus in College Lane, improvements to the site‐wide BMS system and replacement lighting for some of the buildings, which are used 24 hours a day.

Lecture Hall

OUR APPROACH

Initially, LCE was asked to review the University’s existing energy metering system and develop a strategy for improving it, so all energy being used on site is effectively monitored.


LCE also undertook a review of the University’s existing BMS system. The review focused on some of the most energy‐intensive buildings, identifying possible improvements to plant control, which helped reduce energy consumption.


We also assisted the University in the general management and reporting of the energy it currently uses. This has included validating utility invoices, assisting with FIT applications for PV installations and providing energy advice on new developments for the University’s capital projects team.

OUTCOMES

LCE’s initial review of the BMS only focused on two buildings, out of a total of more than 30, but it was able to identify a possible reduction in carbon emissions of 360 tonnes through improved plant control.


A preliminary review of the utility invoices also identified that the University was paying for services from their electricity supplier, which they were not using.


By adjusting this service, LCE helped the University save more than £50,000 a year.


The University’s existing metering strategy meant they were reliant on estimated billing from their suppliers, there were gaps in their sub‐metering coverage and some buildings had not been billed since their construction.


LCE’s site survey identified how the sub‐metering coverage could be improved to provide a more complete picture of all the energy being used.


LCE also worked with the University to improve the efficiency of the existing CHP system by implementing the CHPQA programme.


In addition, FIT applications for an existing PV installation have been submitted and the University is now receiving payments from their electricity supplier.

GET IN TOUCH

We would love to hear from you and chat through how our services can help. Or if you want to hear from us then please subscribe to our mailing list.

Picture2.png
2022 - cyberessentials_certification mark_colour .png
6.png
Iheem logo copy.png
bottom of page